All permanent restoration of pavement shall be done by the permittee.
The pavement is to be cut with a spade or a pavement saw. The backfill
shall be placed in six-inch layers and compacted to 95% of AASHO standards
until the excavation has been filled to the grade of existing pavement.
This grade shall be maintained opened to traffic for a minimum of
seven days, after which, the top six inches shall be excavated and
filled with asphalt concrete, Type 7 (top coarse), as defined in the
New York State Department of Transportation standard specifications
to the grade of the existing pavement. All asphalt is to be compacted.